• News
  • Press Releases
  • Renewable News
  • Wind

Sulzer investments further improve speed and quality of high voltage coil manufacturing


Reducing the time to complete a repair or refurbishment of high voltage equipment minimizes downtime and increases productivity. Sulzer is continuing to invest in its design, manufacturing and testing facilities to enable faster turnarounds for customers. To keep up with growing demand, Sulzer is also increasing the capacity of its Falkirk Service Center, where the test-bed load capacity has been doubled.

Until now, the Falkirk site has used a 1’250 kVA diesel generator that operates through two step-up transformers to provide 3.3 – 11 kV via high voltage switchgear to the test cell. This setup ensures a reliable power source for testing that is not affected by local demand on the power grid.

The new investment by Sulzer will add a 2’000 kVA and a 700 kVA generator to the site that will be synchronized through a 4’000 amp low voltage switchboard, as well as a new 2’500 kVA transformer, that will double the capacity of the test bed.

2 MW load testing

The original capacity of the service center was 1’000 kW in load testing, of which 800 kW could be used for testing vertically-orientated motors, across a full range of voltages from 400 V up to 11 kV at both 50 and 60 Hz. The installation of the new equipment will increase the load testing capacity to 2’000 kW for horizontally-orientated motors as well as an increase in voltage to 13.8 kV. The majority of the equipment tested in the additional capacity will be large, high voltage, AC motors, but the possibility to test DC motors up to 600 V, with a loading up to 800 amps will still remain.

Furthermore, an additional test-bed area is now in place to allow multiple motors to be tested alongside each other. This means that if the testing of one motor needs to be extended, it will not hold up other projects, allowing equipment to be returned to customers on time.

The new test bed offers customers the possibility of load testing generators using a slave motor to turn the generator and connecting the output to a load bank. In this way, generators that have undergone major repairs can be tested to ensure that they are fit for purpose before they are re-installed and recommissioned.

Improved customer experience

As part of this upgrade project, the test area is equipped with the latest monitoring controls and safety equipment that provide the test engineers with remote visualizations of the sensor readings while protecting them from large pieces of rotating equipment. A customer viewing area is also available, from where owners of equipment can watch and interact with the test engineers to ensure that the entire process is transparent and straightforward.

Marc Stuart, Service Center Manager, at Sulzer’s Falkirk site comments: “In the past, only equipment that had undergone a major repair would have received a full-load performance test. Now, more and more customers are requesting full-load testing following an overhaul, giving them complete peace of mind that the equipment is fit for purpose.

“Our customers are now able to see their motor operating at load and can review a complete set of test results, including vibration analysis, partial discharge, motor current signal analysis (MCSA) and other condition monitoring data. This is providing our customers with confidence, not only in the performance of the motor but in the service solutions they are receiving. A full test report can then be issued, providing a baseline set of data that they can use once their equipment is installed and running in its application.”

Investment in cutting-edge facilities

Sulzer’s investment program in the UK has delivered a range of new equipment and machinery including replacement looping machines, shaping machines and a state-of-the-art robotic taping machine that will together provide enhanced precision, quality and speed in the manufacture of HV coils.

A major investment has also been made in the design and testing capabilities at Sulzer, with the creation of a ‘Coil Test Lab’ that will enable voltage endurance and thermal cycling tests to be carried out in-house. These tests can determine the durability and expected lifetime of HV coils and ultimately provide a quality rating for the insulation system.

The final step in the repair process for high voltage machines is balancing the rotors to ensure smooth and reliable operation, especially during start-up and shutdown procedures. Sulzer has one of the only independent high-speed balancing facilities in the UK and it has recently been updated with the installation of CABFLEX3 software and additional hardware that will significantly reduce the time required to balance a flexible rotor.

Sulzer continues to invest in its facilities across the country to improve the speed of service to its customers and to ensure the highest quality repairs are delivered.

To see the video showing details of the Falkirk facilities, visit: https://youtu.be/CfnvgiJm1T8

About Sulzer

Sulzer is the leading worldwide, independent service provider for large rotating equipment. With technically advanced and innovative service and maintenance support solutions, Sulzer provides a turnkey service that provides its customers with the peace of mind to focus on their core operations.

Included in this package is a highly efficient and dependable high-voltage coil manufacturing and supply service, delivered from a purpose built facility within the Birmingham Service Centre, UK. It is recognized for producing very high quality coils for high voltage motors and generators; designed, manufactured and shipped by a highly skilled and dedicated team to ensure fast and reliable service.

With an in-house copper rolling mill, Sulzer customers can benefit from round-the-clock manufacturing to ensure that every coil is delivered on schedule. In conjunction with constant quality control and full HV on-site testing facilities, Sulzer can deliver quality, precision and speed, any time, day or night.

For further information click here