Next wave of renewables construction to drive surge in complex insurance claims – GCube report


  • New report analyses 10 years – and USD $1 billion – of global construction claims, highlighting correlation between rapid expansion of renewables and increased construction losses
  • Contractor error and defects account for over half of global offshore construction claims, while onshore claims are being driven by severe Nat Cat and extreme weather
  • Historic ‘boom and bust’ cycle of renewables construction underlines the need to learn from past mistakes, ahead of the next global construction ‘boom’

 

London, 10th September 2024 — As the renewables sector enters a new wave of global construction activity, the build out of projects continues to be jeopardised by contractor errors and defects, Nat Cat and extreme weather events. These challenges, both on- and offshore, may lead to delayed project start times and drive a surge in construction claims, which are among the most complex for insurers and asset owners to settle.

This is according to a new market insights report produced by GCube Insurance, entitled “Arrested Development: Managing complex claims in the boom-and-bust world of renewables construction”. The report shares key findings from a decade of proprietary claims data, including $1 billion in Construction All Risks (CAR) and Delay in Start Up (DSU) claims for onshore and offshore sectors, along with insights from industry experts.

These findings include:

  • Contractor error and defect continue to be the major root causes of offshore wind losses – representing 63% of claims by frequency in 2022, up from 55% in 2020
  • Historically, increased offshore construction activity has been matched by a surge in insurance claims, forming a cyclical ‘boom and bust’ pattern
  • 48% of onshore (wind and solar) construction losses by severity are attributable to Nat Cat and extreme weather, followed by contractor error and defect at 16%
  • Of weather-related losses, flooding and heavy rainfall prove to be the costliest weather events, representing 18% of total claims by frequency but 46% of the total claims cost

 

These construction claims trends broadly mirror the picture for operational projects. However, the impact of losses from both human error and weather-related events on construction projects can be far greater – leading to more complex and costly insurance claims.

While the nature of construction losses is relatively constant, new projects also face increased risk of loss from two sources: one, the higher frequency of extreme weather, the other, the penetration into emerging markets, like the US, MENA, and Asia, where there is less data to guide strong project management.

Fraser McLachlan, Founder & CEO, GCube, said: “The appetite for installing new projects makes this a historically busy period for the renewables sector. It’s also a period marked by unprecedented Nat Cat threat, and a shortage of skilled workers and specific installation equipment, like vessels and cranes. What this means is that the Delay in Start Up (DSU) claims process for a loss in the construction phase will only become more complicated.”

GCube’s data highlights lessons from the past that the renewables sector must heed. The target for offshore construction must be longer-term sustainability, prioritising successful project outcomes over rapid expansion, and supported by a growing pool of skilled contractors and specialist vessels. Meanwhile, the target for onshore construction must be to prevent Nat Cat losses being compounded by human errors arising from the race to scale up technology– a challenge documented in GCube’s 2023 “Vertical Limit” report.

As construction activity ramps up in the coming months, GCube’s core recommendations to asset owners seeking to mitigate potential losses include:

  • Having a robust baseline project plan supplemented by thorough project monitoring
  • Understanding the insurance policy and seeking expert advice where required
  • Developing trusted contacts in the supply chain to ensure quality control

 

McLachlan added: “Over the past few decades, GCube has witnessed first-hand how boom and bust cycles manifest in pressure on the supply chain and culminate in contractor error and defect issues. This, in turn, has led to a more cautious approach from underwriters.”

“However, the forthcoming period of construction activity – and the rising impact of extreme weather – requires a high concentration of risk management, insurance and claims expertise as the industry braces itself for an inevitable increase in losses. Pivotal to minimising project disruption and unbudgeted expense will be the collaboration of insureds and insurers to exchange information and expertise throughout the project lifecycle – this is the key message of our latest report.”

About GCube:

GCube is a leading insurance underwriter for global renewable energy projects, on- and offshore. With over 25 years’ experience in the renewable energy sector, GCube understands the unique exposures of these power generation projects and assists its clients in identifying, quantifying and mitigating risk efficiently and economically while helping them achieve their business objectives.   

GCube is a trading name used by the Tokio Marine HCC group of companies headquartered in Houston, Texas and operates:

· in the United States through GCube Insurance Services, Inc. (California license number 0B86549

· in the United Kingdom through: 

o HCC International Insurance Company plc (company     number 01575839) 

o HCC Underwriting Agency Ltd (company number 04632146) 

o Houston Casualty Company (UK Branch) (Branch registration number BR004760), 

each authorised by the Prudential Regulation Authority (PRA) and regulated by the Financial Conduct Authority (FCA) and the PRA and registered office address at 1 Aldgate, London, EC3N 1RE 

· in Europe through Tokio Marine Europe SA (company number B221975) authorised by the Luxembourg Minister of Finance and regulated by the Commissariat aux Assurances, with registered address at 26 Avenue de la Liberte, Luxembourg, L-1930

To learn more about how we can support your insurance coverage requirements, please visit our website at www.gcube-insurance.com     

Media Contact:

Email: gcube@tamarindo.global 

Phone: 020 7100 1616