Delays to offshore load testing can have knock-on effects across a project programme. Safe Lifting explores how early technical decisions, equipment compatibility and clear responsibilities help teams avoid last-minute issues and keep mobilisation on track.
A load test may take up only a short part of a vessel’s schedule, but preparing for it starts much earlier. Equipment needs to be selected, rigging arrangements checked, test weights organised and the right people available. By the time the crane is ready, all of this should already be in place.
For offshore wind projects, this preparation belongs in the main programme. Testing and mobilisation sit between engineering decisions and operational delivery. Leaving either until the final stages can mean important questions are still unresolved when the equipment arrives at the quay.
The useful question is therefore broader than whether equipment can be delivered on a particular date. Can the complete package be assembled, checked and used for the intended operation, with the necessary information available to the people responsible? That is the point at which equipment availability becomes operational readiness.
Define the test before selecting the equipment
A request for test equipment should begin with what the test is intended to demonstrate. The required load, test configuration, loading sequence, acceptance criteria and reporting requirements need to be established by the responsible specialists under the applicable technical requirements. These decisions shape the equipment package and the work around it.